PSM I Exam - Question 161


Which two things should the Scrum Team do during the first Sprint? (Choose two.)

Show Answer
Correct Answer: CDE

During the first Sprint, the Scrum Team should focus on delivering valuable functionality and creating a potentially shippable product Increment. This aligns with the principles of Scrum, which emphasize iterative development and delivering value to stakeholders early and often. Therefore, building at least one piece of valuable functionality and creating at least one valuable, useful Increment are the primary objectives.

Discussion

10 comments
Sign in to comment
imEmiOptions: CE
May 10, 2023

It should be CE

BhaloOptions: CE
May 24, 2023

Right answer is C & E

ObeObeObeOptions: CE
May 27, 2023

Agree with C & E

George103Options: CE
Jun 26, 2023

C And E!

Numba1Options: CE
Jun 2, 2023

that's the answer

AlbinopretoOptions: BE
Aug 1, 2023

<B. Définir les principales fonctionnalités du produit et une architecture de plan de version. E. Créez au moins un incrément précieux et utile. Lors du premier Sprint, l'équipe Scrum travaille sur une sélection de fonctionnalités préalablement définies dans le Product Backlog, et elle doit se concentrer sur la création d'un incrément de produit fonctionnel, utile et potentiellement livrable. L'équipe commence également à planifier la manière dont les fonctionnalités seront développées et livrées dans les versions futures (plan de version), ce qui est essentiel pour guider le développement tout au long du projet Scrum. Les autres options ne sont pas des activités typiques du premier Sprint.

Jyoti1010Options: CE
Oct 2, 2023

C and E

ceausorinOptions: CE
Oct 14, 2023

Agree with C & E

GatapardaOptions: CE
Nov 18, 2023

Based in Scrum Guide 2020 C & E

emelbaOptions: CE
Dec 31, 2023

D is incorrect