PSM I Exam - Question 85


When is the Sprint Backlog created?

Show Answer
Correct Answer: B

The Sprint Backlog is created during the Sprint Planning meeting. This meeting is held at the beginning of each Sprint, where the Scrum team determines the work to be completed during the upcoming Sprint. The Sprint Backlog includes all the tasks and items that the team commits to achieving during that specific Sprint.