PSM II Exam QuestionsBrowse all questions from this exam

PSM II Exam - Question 164


How much time is allowed between the conclusion of the current Sprint and the start of the next Sprint?

Show Answer
Correct Answer: B

In Scrum, a new Sprint starts immediately after the conclusion of the previous Sprint. There is no break or gap between Sprints. This ensures a continuous flow of work and maintains the rhythm of the development process.

Discussion

1 comment
Sign in to comment
amogOption: B
Mar 10, 2021

B is correct