Question 100

What would be typical Scrum Master activities during the Sprint?

    Correct Answer: B

    A typical Scrum Master activity during the Sprint includes removing impediments and facilitating inspection and adaptation opportunities as requested or needed. This aligns with the Scrum framework where the Scrum Master acts as a facilitator and coach, ensuring the Development Team has everything they need to meet their goals and helping to remove any barriers that could impede the team's progress.

Discussion
nhungnt184Option: B

Yes, B.

amogOption: B

B is correct