PSM II Exam - Question 51


If burndown charts are used to visualize progress, what does a trendline through a release burndown chart indicate?

Show Answer
Correct Answer: C

A trendline through a release burndown chart projects the completion date based on the remaining work and the team's current progress rate. It estimates when the work will be finished if there are no changes to the Product Backlog or the Development Team's productivity, making it a useful tool for planning and tracking progress.

Discussion

1 comment
Sign in to comment
amogOption: C
Mar 9, 2021

C is the answer