PSM II Exam - Question 88


The Development Team discovers that it doesn't have the tools and infrastructure to make each selected Product Backlog item done.

What is the most appropriate action for the Scrum Master to take?

Show Answer
Correct Answer: C

The most appropriate action for the Scrum Master is to coach the Development Team to improve its skills, tools, and infrastructure over time and establish a Definition of 'Done' that is actually possible to achieve given the current circumstances. The Scrum Master's role includes fostering self-organization and continuous improvement within the team, which aligns with guiding the team to enhance their capabilities and realistically define their Definition of Done.