When is implementation of a Product Backlog item considered complete?
When is implementation of a Product Backlog item considered complete?
Implementation of a Product Backlog item is considered complete when the item has no work remaining in order to be potentially released. This aligns with the Scrum framework's Definition of Done, which ensures that the item is fully developed, tested, and meets all acceptance criteria, leaving no further tasks to be performed. This guarantees that the item is ready for deployment to the production environment.
"Each Increment is additive to all prior Increments and thoroughly verified, ensuring that all Increments work together."