PSM I Exam QuestionsBrowse all questions from this exam

PSM I Exam - Question 107


True or False: The Product Owner makes sure the Developers select enough from the Product Backlog for a Sprint to satisfy the stakeholders.

Show Answer
Correct Answer: B

False. The Product Owner does not ensure that the Developers select enough from the Product Backlog for a Sprint to satisfy the stakeholders. Instead, the Developers themselves are responsible for selecting the amount of work they can complete within a Sprint. The Product Owner ensures that the backlog is prioritized and clearly communicated but does not dictate how much work the Developers should commit to.

Discussion

2 comments
Sign in to comment
Mi_WindsorOption: B
Aug 12, 2023

B - False

Jyoti1010Option: B
Oct 14, 2023

Developers pull items from product backlog.items are not pushed.