PSM II Exam - Question 21


What is management's role in Scrum?

Show Answer
Correct Answer: A

Management's role in Scrum is to provide the necessary environment and support as defined by the Scrum Guide by offering insights and resources that help Scrum Teams continue moving forward. This involves creating conditions that enable the Scrum Team to function effectively, which aligns with fostering empiricism, self-organization, and promoting a productive and collaborative atmosphere.

Discussion

5 comments
Sign in to comment
amog
Mar 9, 2021

A is the answer

lenanguyen89
May 26, 2023

A is correct

Mi_Windsor
May 17, 2024

A is correct

MbouzidiOption: A
Jul 25, 2024

A is correct

EdmundLYMOption: A
Apr 5, 2025

The answer is true. Key Points Supporting "True": - Scrum emphasizes starting with what is known and refining as you go. - A fully detailed Product Backlog is not required before starting the first Sprint. - The three roles (Product Owner, Development Team, Scrum Master) are sufficient to initiate the process.