PSM II Exam QuestionsBrowse all questions from this exam

PSM II Exam - Question 37


By the end of the Sprint, a Product Backlog item in the Sprint Backlog does not meet the team's Definition of Done.

What two things should happen with the item? (Choose two.)

Show Answer
Correct Answer: BD

At the end of a Sprint, any Product Backlog item that does not meet the team's Definition of Done should not be included in the Increment, ensuring that the Increment remains in a usable and potentially releasable state. The remaining work needed to complete the item should be estimated and added back to the Product Backlog, allowing the Product Owner to prioritize it for future Sprints. This approach maintains a clear distinction between completed and incomplete work and upholds the integrity of the Scrum process.

Discussion

3 comments
Sign in to comment
amogOptions: BD
Mar 9, 2021

Follow the Scrum Guide B and D are correct

Edgecrusher77Options: AD
Feb 11, 2021

Not sure about this one, should be A & D. If it's accepted by stakeholder, it can be accepeted in the increment, they are the one judging the end product.

avk
Mar 9, 2021

As the item is not meeting DoD so it cant be considered for increment. And i feel it should be shown to the stakeholder too.

Mi_WindsorOptions: BD
Jul 26, 2023

B and D are the best answer