PSM II Exam QuestionsBrowse all questions from this exam

PSM II Exam - Question 167


Which of the following are time-boxed events in Scrum?

Show Answer
Correct Answer: E

In Scrum, all the mentioned events are time-boxed. Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint. Daily Scrum is time-boxed to 15 minutes. Sprint Review is time-boxed to a maximum of four hours for a one-month Sprint. Lastly, Sprint Retrospective is time-boxed to a maximum of three hours for a one-month Sprint. Therefore, all of the above is the correct answer.

Discussion

1 comment
Sign in to comment
amogOption: E
Mar 10, 2021

E is correct