PSM I Exam - Question 114


The Scrum Master observes the Product Owner struggling with ordering the Product Backlog. What is an appropriate action for the Scrum Master to take?

Show Answer
Correct Answer: C

The Scrum Master should offer the Product Owner help in understanding that the goal of ordering the Product Backlog is to maximize value. This approach empowers the Product Owner to fulfill their responsibility and supports effective Product Backlog management without undermining their authority.

Discussion

9 comments
Sign in to comment
Bj2
Mar 23, 2022

It should be C - the PO is owner of the product backlog and therefore the scrum master could help him to identify value therefore enable him to order by himself.

L33roi
Mar 24, 2022

It's C 🤓

correct_to_a_t
Mar 28, 2022

Dev team never orders the Product Backlog - its C

iduser
Mar 11, 2022

why not C?

AshishJ100583
Mar 13, 2022

I also agree, It should be C

AshishJ100583
Mar 13, 2022

I read the guide and realised it should be B. The guide says, Scrum master serves product owner in finding techniques for effective product backlog management. This easliy relates to B

beauchamp
May 9, 2022

Therefore B is not correct. as B i suggesting Dev. team, it should be PO.

Joshalom
May 12, 2023

Correct answer is C

Jyoti1010Option: C
Sep 29, 2024

Correct answer is C

dinuse123Option: C
Dec 13, 2024

Product Owner comes up with the requirement. So, Scrum master can inform him/her to provide the right backlog items.