PSM I Exam QuestionsBrowse all questions from this exam

PSM I Exam - Question 11


Which of the following is required by Scrum?

Show Answer
Correct Answer: A

Sprint Retrospective is a required event in the Scrum framework. Members do not need to stand up at the Daily Scrum, as posture is not prescribed. A Sprint Burndown Chart is a tool that can be used to track progress but is not mandatory. Release planning is useful but not specifically mandated by Scrum.

Discussion

17 comments
Sign in to comment
MordsithOption: A
Apr 8, 2021

the answer is A. because scrum framework does not have the rest as a must use.

Sayed_AboshamaOption: A
Jul 31, 2023

The answer should be A. The other choices are not required for SCRUM

VishlancerOption: A
Jul 22, 2023

Answer is "A": "Sprint Burndown Chart" is not the have thing in SCRUM, it's one of the ways to measure the team's capabilities in handling the Items and the leftover time to complete the sprint. Basically, it's one of the metrics that can be captured to identify the Sprint progress.

sakkalOption: A
Aug 7, 2023

A is the answer

PRINZVONBRAZILIENOption: A
Oct 18, 2023

The answer is A, the others is not REQUIRED, its only a plus.

Kay15Option: B
Jun 27, 2023

Also in the 2020 version they specifically said they're no longer calling daily scrum meetings "stand-up" meetings because it makes people assume they have to stand up - which they don't. And not everyone can stand up.

miubabyOption: A
Sep 24, 2023

A is the correct answer

wax_gibbousOption: A
Nov 6, 2023

The C and D are not even in the Scrum Guide and B is a must but the guide doesn't prescribe any such thing as standing up

mfreakOption: A
Dec 3, 2023

I believe it's A

MarcoScaramelliOption: A
Feb 21, 2024

A. is the correct one, others not required

Mi_WindsorOption: A
Jul 30, 2023

A is the correct answer

Jyoti1010
Sep 26, 2023

Sprint,Sprint planning,Daily Scrum,Sprint review and Sprint retrospective are the 5 events part of Scrum.

tinku_bowmanOption: A
Oct 15, 2023

the others are not required

MicoppOption: A
Oct 21, 2023

Whichever tool or method is felt appropriate to measure sprint progress can be used - not necessarily burn down chart - so this invalidates suggested answer D. ....Agile Manifesto - "working software (I will insert increments for this purpose :) ) is the best measure of progress".

DjedjigOption: A
Feb 19, 2024

A is correct

dehbashi.projectOption: A
May 2, 2024

The true answer is " A " Actually Scrum without options B and C and D is Scrum, but without A, it's not.

dehbashi.project
May 2, 2024

B. The development team is enough for daily stand ups C. Dose not a requirement D. Dose not a requirement

RolianiOption: A
Jul 5, 2024

A is the correct answer. SCRUM does not require the other options.