Question 11

Which of the following is required by Scrum?

    Correct Answer: A

    Sprint Retrospective is a required event in the Scrum framework. Members do not need to stand up at the Daily Scrum, as posture is not prescribed. A Sprint Burndown Chart is a tool that can be used to track progress but is not mandatory. Release planning is useful but not specifically mandated by Scrum.

Discussion
MordsithOption: A

the answer is A. because scrum framework does not have the rest as a must use.

Sayed_AboshamaOption: A

The answer should be A. The other choices are not required for SCRUM

PRINZVONBRAZILIENOption: A

The answer is A, the others is not REQUIRED, its only a plus.

sakkalOption: A

A is the answer

VishlancerOption: A

Answer is "A": "Sprint Burndown Chart" is not the have thing in SCRUM, it's one of the ways to measure the team's capabilities in handling the Items and the leftover time to complete the sprint. Basically, it's one of the metrics that can be captured to identify the Sprint progress.

MarcoScaramelliOption: A

A. is the correct one, others not required

mfreakOption: A

I believe it's A

wax_gibbousOption: A

The C and D are not even in the Scrum Guide and B is a must but the guide doesn't prescribe any such thing as standing up

miubabyOption: A

A is the correct answer

Kay15Option: B

Also in the 2020 version they specifically said they're no longer calling daily scrum meetings "stand-up" meetings because it makes people assume they have to stand up - which they don't. And not everyone can stand up.

RolianiOption: A

A is the correct answer. SCRUM does not require the other options.

dehbashi.projectOption: A

The true answer is " A " Actually Scrum without options B and C and D is Scrum, but without A, it's not.

dehbashi.project

B. The development team is enough for daily stand ups C. Dose not a requirement D. Dose not a requirement

DjedjigOption: A

A is correct

MicoppOption: A

Whichever tool or method is felt appropriate to measure sprint progress can be used - not necessarily burn down chart - so this invalidates suggested answer D. ....Agile Manifesto - "working software (I will insert increments for this purpose :) ) is the best measure of progress".

tinku_bowmanOption: A

the others are not required

Jyoti1010

Sprint,Sprint planning,Daily Scrum,Sprint review and Sprint retrospective are the 5 events part of Scrum.

Mi_WindsorOption: A

A is the correct answer