PSM I Exam - Question 149


Which topics should be discussed in the Sprint Review?

Show Answer
Correct Answer: AC

The primary focus of the Sprint Review is to inspect the product Increment and adapt the product backlog if needed. This review provides an opportunity for the Scrum Team and stakeholders to discuss what has been done during the Sprint, review the progress, and adjust the product backlog based on the feedback. Discussions on the Scrum process and engineering practices are more suitable for the Sprint Retrospective.

Discussion

4 comments
Sign in to comment
ObeObeObeOption: C
May 27, 2023

Review not retrospective

milena_gornickaOption: C
Sep 11, 2022

On the Sprint Review the increment should be the main topic. The Scrum Process is the topic for the Sprint Retro.

Jyoti1010Option: C
Oct 2, 2023

C is right choice

6fcf1a4Option: C
Dec 20, 2023

ChatGPT picks C "C. The product Increment. The primary focus of the Sprint Review is to discuss and inspect the product Increment that was developed during the sprint."