Exam PSM I All QuestionsBrowse all questions from this exam
Question 149

Which topics should be discussed in the Sprint Review?

    Correct Answer: C

    The primary focus of the Sprint Review is to inspect the product Increment and adapt the product backlog if needed. This review provides an opportunity for the Scrum Team and stakeholders to discuss what has been done during the Sprint, review the progress, and adjust the product backlog based on the feedback. Discussions on the Scrum process and engineering practices are more suitable for the Sprint Retrospective.

Discussion
ObeObeObeOption: C

Review not retrospective

milena_gornickaOption: C

On the Sprint Review the increment should be the main topic. The Scrum Process is the topic for the Sprint Retro.

Jyoti1010Option: C

C is right choice

6fcf1a4Option: C

ChatGPT picks C "C. The product Increment. The primary focus of the Sprint Review is to discuss and inspect the product Increment that was developed during the sprint."