Question 34

Steven, the Scrum Master, observes that one of the Development Team members is not attending the Daily Scrum. The Development Team feels this is ok as they all sit in the same area and already have constant communication throughout the day.

Which is the best action for Steven to take?

    Correct Answer: C

    The Scrum Master should help the Development Team understand the importance of the Daily Scrum. By asking what value results from having all team members present and what risks are involved if members don't attend, the Scrum Master encourages the team to reflect on the purpose of the Daily Scrum and fosters a team-owned solution within the Scrum framework.

Discussion
Mi_WindsorOption: C

C is correct

amogOption: C

C is correct