What is a Development Team responsible for? (Choose two.)

    Correct Answer: A, D

    The Development Team is responsible for resolving internal team conflicts as they are a self-organizing unit. Additionally, organizing the work required to meet the Sprint Goal is one of their key responsibilities, ensuring they accomplish their objectives by effectively managing their tasks and workflow.

Discussion
AnosaOptions: AD

Correct A&D , SM has to do everything possible to try ( coach) Development Team to resolve conflict

Jyoti1010Options: AD

A and D

hiepnb97Options: AD

A. The Development Team is self-organizing -> resolving internal team conflicts. D. 100%

Mi_WindsorOptions: AD

A and D are correct

manithiyagu

Is correct answer A&D or B&D ? Seems Report productivity also close enough