Which two things should the Development Team do during the first Sprint? (Choose two.)
Which two things should the Development Team do during the first Sprint? (Choose two.)
During the first Sprint, the Development Team should focus on developing at least one piece of functionality to ensure they are delivering value to the customer and validating their approach. Additionally, they should create an increment of potentially releasable software, which embodies the core Scrum objective of delivering usable, working software at the end of each Sprint.
Develop at least one piece of functionality and Create an increment of potentially releasable software
C and E for sure
Option C and E
C and E are the correct answer
C and E
C, E are correct
Take care of how the question was asked. This is a bit misleading because E basically implements the task described in C.
it should be c,e i missed