PSM I Exam - Question 19


Which two things should the Development Team do during the first Sprint? (Choose two.)

Show Answer
Correct Answer: CE

During the first Sprint, the Development Team should focus on developing at least one piece of functionality to ensure they are delivering value to the customer and validating their approach. Additionally, they should create an increment of potentially releasable software, which embodies the core Scrum objective of delivering usable, working software at the end of each Sprint.

Discussion

8 comments
Sign in to comment
dandirindanOptions: CE
Apr 18, 2022

Develop at least one piece of functionality and Create an increment of potentially releasable software

fabianoalessiOptions: CE
Apr 5, 2021

C and E for sure

Naz1Options: CE
Jan 7, 2021

C and E

Mi_WindsorOptions: CE
Jul 30, 2023

C and E are the correct answer

Jyoti1010Options: CE
Sep 26, 2023

Option C and E

dandirindanOptions: CE
Apr 18, 2022

it should be c,e i missed

Ace3301Options: CE
Aug 13, 2023

Take care of how the question was asked. This is a bit misleading because E basically implements the task described in C.

DjedjigOptions: CE
Feb 19, 2024

C, E are correct