Question 157

What Product Owner activities occur between the end of the current Sprint and the beginning of the next Sprint?

    Correct Answer: A

    Product Backlog refinement is an ongoing activity that can occur at any time during the Sprint, including the period between the end of the current Sprint and the beginning of the next Sprint. This activity helps to ensure that the Product Backlog is kept up-to-date with necessary updates and prioritizations.

Discussion
amogOption: C

C is correct