Who does the work to make sure Product Backlog items conform to the Definition of Done? (Choose the best answer.)
Who does the work to make sure Product Backlog items conform to the Definition of Done? (Choose the best answer.)
In Scrum, it is the responsibility of the Developers to ensure that the Product Backlog items conform to the Definition of Done. The Developers are the ones doing the actual work and they ensure that each increment meets the quality standards defined by the team.
C is correct.