Question 13

In Scrum, how would budgeting and financial forecasting be performed? (Choose two.)

    Correct Answer: A, B

    In Scrum, budgeting and financial forecasting are tied closely to the delivery and value assessment of each Sprint. Frequently inspecting the outcomes of the delivered Sprint Increments helps to understand the value being produced per investment spent. This continuous evaluation allows adjustments to be made incrementally, fostering better financial forecasting. Additionally, funding can be planned in alignment with multiple Sprints, each producing shippable increments, ensuring that expenses are managed across releases while consistently delivering potentially releasable products that can provide immediate value.

Discussion
Mi_WindsorOptions: AB

A + B are the correct options

lenanguyen89Options: AB

A & B are my answer

amogOptions: AB

A and B are correct