PSM I Exam - Question 109


Who owns the Sprint Backlog?

Show Answer
Correct Answer: D

The Sprint Backlog is owned by the Development Team. The Development Team is responsible for managing and updating the Sprint Backlog during the Sprint. They are the ones who perform the work and hence, they track the progress and make necessary adjustments.

Discussion

4 comments
Sign in to comment
scrummie123Option: D
Jul 11, 2024

CORRECT ANSWER

Mi_Windsor
Aug 12, 2024

D the development team owns the sprint backlog

Jyoti1010Option: D
Oct 14, 2024

D is correct

BJD1199Option: D
Jan 30, 2025

he Product Owner (PO) is responsible for managing the Product Backlog and ensuring it aligns with the Product Goal. Their key responsibilities include: ✅ Creating and maintaining the backlog – Defining and refining backlog items. ✅ Ensuring visibility – Making sure the backlog is transparent to both stakeholders and the Scrum Team. ✅ Prioritization – Ordering backlog items to maximize value. ✅ Balancing priorities and trade-offs – Managing competing demands from stakeholders, technical constraints, and business needs. ✅ Decision-making – Making tough calls when resources are limited or stakeholder interests conflict. While the Product Owner owns the Product Backlog, the Development Team owns the Sprint Backlog, which consists of selected Product Backlog items for the sprint and the team's plan to complete them. This ensures a clear separation of responsibilities, fostering collaboration while maintaining agility.