Exam PSM II All QuestionsBrowse all questions from this exam
Question 3

Paul is a Product Owner for multiple products. Each product is allocated a dedicated Scrum Team and a set budget. Based on the average velocity of a previous product release, Paul had estimated a new product to take 9 Sprints to complete. The average velocity of the previous product release was 50 completed units of work per Sprint. Over the first 3 Sprints, the Development Team reported an average velocity of 40 completed units per Sprint, while not fully completing the required integration tests. The Development Team estimates that integration testing would require additional effort to make the increments shippable. The

Development Team is unsure if the required velocity is achievable.

What is the most effective way to recover?

    Correct Answer: B

    The Development Team should inform Paul that the perceived progress is not accurate since the increments are not releasable due to incomplete integration tests. They should provide an estimation of the effort required to complete the previously unfinished work and suggest prioritizing this completion before adding new features. Additionally, the team must re-estimate the remaining effort to complete the Product Backlog items, including the necessary integration effort. This approach ensures transparency and allows for informed decision-making based on the current situation. Moreover, it adheres to Scrum principles, emphasizing the need for 'done' increments at the end of every Sprint to facilitate inspection and adaptation.

Discussion
Hana9Option: B

Answer B

Mi_WindsorOption: B

Answer is B.

PaulWaltROption: B

B. PB items need to meet definition of done before they can be released.

amogOption: B

Answer is B