Exam PSM I All QuestionsBrowse all questions from this exam
Question 145

During the Sprint Retrospective a Scrum Team has identified several high priority process improvements. Which of the following statements is most accurate?

(Choose the best answer.)

    Correct Answer: A

    During the Sprint Retrospective, the Scrum Team identifies areas for improvement and determines how to address them to enhance their effectiveness. It is both correct and advisable for the Scrum Team to add high-priority process improvements to the Sprint Backlog for the next Sprint if they deem it necessary. This practice ensures that the team continues to evolve and improve its processes continuously.

Discussion
JoshalomOption: A

A - The Scrum Team identifies the most helpful changes to improve its effectiveness. The most impactful improvements are addressed as soon as possible. They may even be added to the Sprint Backlog for the next Sprint. SG2020

greisymilenOption: B

Should be the B. Scrum guide says: ". The most impactful improvements are addressed as soon as possible. They may even be added to the Sprint Backlog for the next Sprint."

JohnnyP

It is A based on the 2nd half of the guide "They may even be added to the Sprint Backlog for the next Sprint" - with the emphasis on "may even", which implies that this is the earliest

EgycrmDev

Not B Only the PO can modify the product backlog

tim_range

They're modifying the Sprint Backlog, not the Product Backlog. PO owns Product Backlog, development team owns Sprint Backlog

UppersquareCapitalOption: A

Correct Answer - A

AmrxOption: A

The most impactful improvements are addressed as soon as possible. They may even be added to the Sprint Backlog for the next Sprint.

DDSOption: A

'A' : The Scrum Guide(2020) Sprint Retrospective - The Scrum Team identifies the most helpful changes to improve its effectiveness. The most impactful improvements are addressed as soon as possible. They may even be added to the Sprint Backlog for the next Sprint

xcjxcjOption: B

Team should add to product backlog and let product owner decide the priority

xcjxcj

And sprint backlog created in sprint planning.(next sprint)