PSM II Exam - Question 155


A key concern when multiple Development Teams are working for the same Product Backlog is minimizing dependencies between teams.

Show Answer
Correct Answer: A

Minimizing dependencies between multiple Development Teams working on the same Product Backlog is critical. It helps to reduce complexity, avoid bottlenecks, and allows teams to operate more independently and efficiently. This improves overall agility and facilitates smoother integration of work done by different teams.