Question 83

Which three of the following are feedback loops in Scrum? (Choose three.)

    Correct Answer: A, C, E

    Sprint Review, Sprint Retrospective, and Daily Scrum are key feedback loops in Scrum. Sprint Review allows for feedback on the increment produced during the sprint, Sprint Retrospective focuses on feedback to improve the process and teamwork, and Daily Scrum is a daily feedback loop for the team to inspect progress and adapt their plan.

Discussion
Jyoti1010Options: ACE

Correct

Mi_WindsorOptions: ACE

A C E are correct