When do Development Team members take ownership of a Sprint Backlog item? (Choose the best answer.)
When do Development Team members take ownership of a Sprint Backlog item? (Choose the best answer.)
C
Reference:
https://www.vivifyscrum.com/insights/sprint-backlog-basics-and-faq#:~:text=When%20does%20a%20Development%20Team,mean%20they%
20become%20the%20owner
As "The Sprint Backlog is a plan by and for the Developers." i think the answer is Option A.
The answer is literally in your comment and you still choose A....
C is the correct answer
Option C
According to the Scrum Guide, "Sprint Planning addresses the following topic: What can be Done this Sprint? ...Through discussion with the Product Owner, the Developers select items from the Product Backlog to include in the current Sprint."
That's talking about selecting items to include in the sprint, but the question is who owns the sprint backlog and that's the developers as a whole.
C is correct
It caused me doubts, beetwen A and C.
It's C. This is a question in the practice exam on scrum.org.
its C! i'm 100% sure
It's C
C, sprint Backlog is never owned by an individual but by all developers
C is correct