Exam PSM I All QuestionsBrowse all questions from this exam
Question 115

Which two things are appropriate for a Scrum Master to do if the Scrum Team doesn't have the tools and environment to completely finish each selected Product

Backlog item? (Choose two.)

    Correct Answer: A, E

    The Scrum Master should focus on coaching the Scrum Team to improve its skills, tools, and infrastructure over time, and adjust the Definition of Done accordingly. Additionally, the Scrum Team needs to establish a Definition of Done that is possible to achieve given the current circumstances while gradually improving it. Both actions help in progressively enhancing the team's capability to complete each selected Product Backlog item within the constraints they face.

Discussion
hiepnb97Options: AE

AE "If the Definition of Done for an increment is part of the standards of the organization, all Scrum Teams must follow it as a minimum. If it is not an organizational standard, the Scrum Team must create a Definition of Done appropriate for the product." Scrum Master "Coaching the team members in self-management and cross-functionality."

Jyoti1010Options: AE

A and E