Exam PSM II All QuestionsBrowse all questions from this exam
Question 45

After several Sprints, a key stakeholder starts using the product. The stakeholder is surprised by the slow performance and complains to the Product Owner. The

Product Owner comes to the Scrum Master asking for advice.

What is the best action for a Scrum Master to take?

    Correct Answer: D

    The best action for a Scrum Master to take is to encourage the Product Owner to bring the performance concerns to the Development Team and work with them on how to improve performance, and ultimately have stronger Definition of Done. This approach promotes collaboration between the Product Owner and the Development Team to address the performance issue directly and ensures that the Definition of Done is updated to include performance standards. Waiting until the next Sprint Retrospective might delay addressing the issue, while involving the testers directly or leaving it solely up to the Development Team might not fully engage the stakeholders in the solution.

Discussion
Coco001Option: D

For answer D when is this done, when is the DOD reviewed, isn’t not during retrospective?