PSM II Exam - Question 105


What action should a Scrum Master take if the Development Team has decided that Retrospectives are no longer necessary?

Show Answer
Correct Answer: A

Retrospectives are a critical part of the Scrum framework and are essential for continuous improvement within the team. If the Development Team has decided that Retrospectives are no longer necessary, it is the Scrum Master's responsibility to ensure that these meetings remain productive and beneficial. By facilitating more productive and useful Retrospectives, the Scrum Master can help the team see the value in these sessions and encourage continuous improvement.

Discussion

1 comment
Sign in to comment
amogOption: A
Mar 10, 2021

A is correct