PSM I Exam - Question 62


For the purpose of transparency, when does Scrum say a valuable and useful increment must be available? (Choose the best answer.)

Show Answer
Correct Answer: D

Scrum mandates that a valuable and useful increment must be available at the end of every Sprint. This ensures continuous delivery of potentially shippable product increments which fosters transparency, inspection, and adaptation.

Discussion

2 comments
Sign in to comment
Mi_WindsorOption: D
Aug 10, 2023

D is the correct answer

Jyoti1010Option: D
Sep 26, 2023

D is correct