When must the Product Owner participate in the Daily Scrum?
When must the Product Owner participate in the Daily Scrum?
The Product Owner only participates in the Daily Scrum when they are actively working on items in the Sprint Backlog; in this case, they participate as a Developer. The Daily Scrum is primarily meant for the Developers to synchronize their work and plan for the day. Therefore, the correct scenario where the Product Owner is required to participate is when they are contributing directly to the development work as a Developer.
Daily scrum is for developers.D is the right answer.Scrum master and Product owner attend daily scrum only If they are working on sprint backlog item.They participate as developer.
D. Lorsque le Product Owner travaille activement sur des éléments du Sprint Backlog ; cependant, ils participent en tant que développeur. Le Daily Scrum est une réunion quotidienne du Scrum où les membres de l'équipe de développement se réunissent pour synchroniser leur travail et planifier les activités pour la journée. Le Product Owner peut participer au Daily Scrum en tant qu'observateur, mais il ne doit pas être considéré comme une partie prenante régulière de cette réunion car il n'est pas directement impliqué dans la réalisation des tâches quotidiennes.
Answer D, according to scrum guide .
If the Product Owner or Scrum Master are actively working on items in the Sprint Backlog, they participate as Developers. If the Scrum master or product owner is actively working on product backlog items, he or she is expected to both attend and participate in the daily Scrum
Agree with A
This answer is incorrect. it should be A
Scrum Guide says If the Product Owner or Scrum Master are actively working on items in the Sprint Backlog, they participate as Developers.
The correct answer is A