Question 87

What guideline should the Scrum Master provide if the Product Owner asks how estimations should be made in Scrum?

    Correct Answer: C

    In Scrum, the Development Team is responsible for making the estimates as they are the ones who will be doing the work and have the most accurate understanding of the effort required. This approach ensures that estimates are realistic and based on the team's experience and capabilities.

Discussion
nhungnt184Option: C

Yes, C.

amogOption: C

C is correct