PSM II Exam QuestionsBrowse all questions from this exam

PSM II Exam - Question 169


Which statement is correct about the length of the Sprints?

Show Answer
Correct Answer: A

All Sprints must be one month or less and it is optimal to have a consistent Sprint length. This reflects the Scrum framework's guidelines which specify that a Sprint should not exceed one month. Consistent Sprint lengths help teams maintain a regular cadence, which aids in planning, tracking progress, and measuring performance.

Discussion

1 comment
Sign in to comment
amogOption: A
Mar 10, 2021

A is correct