Question 17

Who creates the definition of `Done`?

    Correct Answer: B

    The Definition of Done is created by the Scrum Team as a whole, which includes the Product Owner, Scrum Master, and Development Team. This collective effort ensures that the definition reflects a shared understanding and commitment. In cases where an organizational standard exists, Scrum Teams must follow it as a minimum baseline; however, if no such standard exists, the Scrum Team collaboratively creates one appropriate for the product. This approach emphasizes the Scrum framework's core values of collaboration and self-organization.

Discussion
therealjimjamOption: B

B is the correct answer

Dilara22Option: B

According to Scrum Guide v2020: If the Definition of Done for an increment is part of the standards of the organization, all Scrum Teams must follow it as a minimum. If it is not an organizational standard, the Scrum Team must create a Definition of Done appropriate for the product. So the answer is B

DjedjigOption: D

D is correct

Richard_35Option: D

Réponse D : on prend celle de l'organisation ou les développeurs en créent une

Jyoti1010Option: D

Option D

dehbashi.projectOption: B

The true answer is " B " (Scrum Guide - Page 12) If it is not an organizational standard, the Scrum Team must create a Definition of Done appropriate for the product.

emelbaOption: D

D. From the Scrum Guide: "If the Definition of Done for an increment is part of the standards of the organization, all Scrum Teams must follow it as a minimum. If it is not an organizational standard, the Scrum Team must create a Definition of Done appropriate for the product. "

can1024Option: D

D. The development organization (or Development Team if none is available from the development organization). First pick organization standard, otherwise the team create its own, which is align with D.

rrr5v3Option: D

D is actually correct. On scrum practice assesment, there's 4 choices for the same question, and B is not selected as correct.

billywooOption: B

"If 'Done' for an increment is not a convention of the development organization, the Development Team of the Scrum Team must define a definition of 'Done' appropriate for the product." (Scrum Guide 2020)

wanae69Option: B

The key word here "Create". So Scrum Team

PAGOption: B

B is the correct answer

SushilctsOption: B

B - " The Definition of Done is managed by the Scrum Team "

wax_gibbousOption: B

DoD is produced by the development team

Prozac400Option: B

Option B is correct. Option D is incorrect because the responsibility for creating the Definition of Done in Scrum lies with the Scrum Team, which includes the Product Owner, Scrum Master, and the Development Team. The Scrum Guide emphasizes collaboration and shared understanding within the Scrum Team. Option D, which suggests that the definition is created by the development organization (or Development Team if none is available from the development organization), is not aligned with the Scrum framework. Scrum places an emphasis on self-organization and cross-functional collaboration within the Scrum Team, and the Definition of Done is a reflection of that collaborative effort.

Issam_KHELILOption: B

I think the correct answer is B

jasM_123Option: B

B is the correct answer