PSM II Exam - Question 176


What might be a valid reason for abnormally cancelling a Sprint?

Show Answer
Correct Answer: D

A valid reason for abnormally cancelling a Sprint is when the Sprint Goal becomes obsolete. This could occur due to changes in business priorities, market conditions, or other external factors that render the original goal irrelevant or unachievable. In such a scenario, continuing with the Sprint would not add value to the product or the organization, and it would be more effective to re-evaluate and plan a new Sprint aligned with the updated objectives.

Discussion

1 comment
Sign in to comment
amogOption: D
Mar 10, 2021

D is correct