PSM I Exam - Question 10


Who can cancel a Sprint?

Show Answer
Correct Answer: C

The Product Owner is the only person who has the authority to cancel a Sprint if the Sprint Goal becomes obsolete. This can happen if there is a change in direction or objectives that makes the current work in the Sprint no longer valuable. The Scrum Master, the Scrum Team, and the Stakeholders do not have the authority to cancel a Sprint.

Discussion

3 comments
Sign in to comment
Jyoti1010Option: C
Sep 26, 2023

Product Owner-C

Mi_WindsorOption: C
Jul 30, 2023

C - the product owner can cancel a sprint

maverick_walkerOption: C
Apr 29, 2024

C - The Product Owner