Question 151

Part of the team's Definition of `Done` requires creating or updating technical documentation in order to maintain the product and/or features in the future. The team's technical writer will be on vacation during the Sprint.

What should you do?

    Correct Answer: B

    Since the team's Definition of Done requires creating or updating technical documentation, it is the responsibility of the Development Team to ensure that the Increment meets these criteria. Even if the technical writer is on vacation, the Development Team still needs to ensure that all aspects of the Definition of Done are completed, including documentation. Therefore, the Development Team members should write the documentation themselves to ensure the work is done in conformance with their Definition of Done.

Discussion
amogOption: B

B is correct