Which two statements are the most accurate in regards to scaling Scrum for large projects requiring multiple Scrum Teams? (Choose two.)
Which two statements are the most accurate in regards to scaling Scrum for large projects requiring multiple Scrum Teams? (Choose two.)
A person focusing on the Sprint Backlog of a single Scrum Team is often more productive because they can concentrate and avoid the context-switching overhead that comes with being involved in multiple teams. A well-structured Product Backlog helps to better organize the work, reducing dependencies and making it possible for team members to concentrate on their allocated tasks without being spread thin across multiple teams. This focus enhances the effectiveness and efficiency of the Scrum Teams working on larger projects.
A and B are the best choice
B eliminate development team members?
C is eliminated as it is very large, D is false it say customizing core scrum framework, which we cant.. so out of for two are eliminated so A and B are correct.