Exam PSM I All QuestionsBrowse all questions from this exam
Question 137

When a Development Team determines that it will not be able to finish the complete forecast, who has to be present when reviewing and adjusting the Sprint work selected? (Choose the best answer.)

    Correct Answer: C

    When a Development Team determines that it will not be able to finish the complete forecast, it is essential for the Product Owner and the Development Team to be present during the review and adjustment of the Sprint work. The Development Team needs to provide insights on progress and technical constraints, while the Product Owner is necessary to negotiate and reprioritize the remaining work to optimize value delivery. This collaboration ensures that the Sprint goals are adjusted appropriately and any necessary trade-offs are agreed upon.

Discussion
Sam_69Option: C

i had the question "When a Development Team determines that it has over-committed itself for a Sprint, who has to be present when reviewing and adjusting the Sprint work selected?" and the right answer is PO + Dev Team

3434343

You had it on PSM1 exam? And had exact words "who has to be present" instead "should be present"?!

Devornasa

IHe is correct, it should be PO + Dev

emelba

If you already took the exam, what are you doing here?

ptoul74Option: C

Another extract from scrum.org open assessment quizz : During a Sprint, a Developer determines that the Scrum Team will not be able to complete the items in their forecast. Who should be present to review and adjust the Product Backlog items selected? (choose the best answer) Correct answer: D) A)The Developers. B) The Scrum Master, the project manager, and the Developers C) The Product Owner and all stakeholders. D) The Product Owner and the Developers.

GiangioOption: C

The answer is C

VoidedSunOption: C

Correct answer should be C. Scrum guide: 1) "Only the Development Team can change its Sprint Backlog during the Sprint" 2) "If the work turns out to be different than the Development Team expected, they collaborate with the Product Owner to negotiate the scope of Sprint Backlog within the Sprint." 3) "The Product Owner can help to clarify the selected Product Backlog items and make trade-offs. If the Development Team determines it has too much or too little work, it may renegotiate the selected Product Backlog items with the Product Owner."

sysopOption: A

Don't be confused by another similar question. The answer for this one is A. This question asked "has to be present", thus, answer is A "Dev". Another question asked "should be present", thus, answer for that question is C "PO + Dev"

Jyoti1010Option: C

Scope renegotiation always occurs in the presence of PO and developers.

sanaw12Option: C

the answer is po+developers

reinefloraOption: C

exam topic, could you give us your opinion ?. from my point of view , the answer is C

MarcoScaramelliOption: C

Answer C is correct

6fcf1a4Option: C

According to ChatGPT, "While not mandatory, it can be beneficial to involve the Product Owner in the discussion"

Jyoti1010Option: C

PO and Development team.

RollizoOption: C

PO and DT analysing in sprint review together It is no talking about during a sprint

JoshalomOption: C

C is correct

cap_examtopicsOption: C

C is the correct answer on the open assessment.

EgycrmDevOption: C

Answer is C

AminaLOption: C

the answer is C