Exam PSM II All QuestionsBrowse all questions from this exam
Question 152

Kevin is a senior developer that has recently joined an existing Scrum Team. The existing team members are unable to get along with Kevin and conclude that he is not a culture fit.

If necessary, who is responsible for removing the new team member, and why?

    Correct Answer: B

    In Scrum, the Development Team is self-organizing and responsible for addressing internal team issues, including resolving conflicts among team members. While the Scrum Master facilitates removing impediments, it is the Development Team that must take the initiative to address and communicate issues, including involving the Scrum Master if they need support. This ensures that the team maintains its self-organizing nature and directly handles its internal dynamics.

Discussion
amogOption: B

B is correct