PSM II Exam QuestionsBrowse all questions from this exam

PSM II Exam - Question 99


How should a Scrum Master coordinate the work when more than one Scrum Team is working on one product?

Show Answer
Correct Answer: A

The Scrum Master should teach the teams that it's their responsibility to coordinate with the other teams to integrate and create a shippable product Increment at the end of every Sprint. This approach aligns with the principles of self-organization and collaboration within Scrum, enabling teams to decide how best to work together to achieve their goals.

Discussion

2 comments
Sign in to comment
amogOption: A
Mar 10, 2021

A is correct

nhungnt184Option: A
Apr 21, 2021

A is correct.