PSM II Exam - Question 146


Which role is responsible for determining when it is most appropriate to update the Sprint Backlog?

Show Answer
Correct Answer: B

The Development Team is responsible for managing their own work and progress during the Sprint. They update the Sprint Backlog as more is learned about the work needed to achieve the Sprint Goal. Therefore, it is the Development Team's responsibility to determine when it is most appropriate to update the Sprint Backlog.