Exam PSM I All QuestionsBrowse all questions from this exam
Question 100

Which two of the following are appropriate topics for discussion during a Sprint Retrospective? (Choose two.)

    Correct Answer: A, C

    The Sprint Retrospective is a meeting held at the end of each Sprint where the team discusses the past Sprint's successes and areas for improvement. Identifying high priority process improvements for the next Sprint and discussing how the team collaborates are appropriate topics for this meeting. These discussions aim to help the team enhance their processes and improve their teamwork for future Sprints. Thus, the correct options are identifying high priority process improvements and how the team collaborates.

Discussion
emelbaOptions: AC

A. Identifying high priority process improvements for the next Sprint. C. How the team collaborates. The Sprint Retrospective is a time for the Scrum Team to reflect on the past Sprint and identify areas for improvement in their processes and collaboration. It is an opportunity to discuss what went well, what could be improved, and how to make those improvements in the upcoming Sprints.

Jyoti1010Options: AC

A and C are right options

Mi_WindsorOptions: AC

A and C are the correct answers