PSM II Exam - Question 162


What could be a reason for a Product Owner to delay the start of a new Sprint after the conclusion of the previous Sprint?

Show Answer
Correct Answer: C

A new Sprint starts immediately after the conclusion of the previous Sprint. This is a fundamental principle of Scrum to ensure a continuous flow of work and adherence to the sprint cadence. There should not be delays between Sprints for any reason, whether it be for testing, stakeholder feedback, or preparing new initiatives. The Scrum framework is designed to maintain a steady rhythm of Sprints to facilitate regular progress and feedback.

Discussion

1 comment
Sign in to comment
amogOption: C
Mar 10, 2021

C is the answer