PSM II Exam QuestionsBrowse all questions from this exam

PSM II Exam - Question 47


At the Sprint Planning, the Development Team is not able to forecast the number of Product Backlog items it can do in the upcoming Sprint due to unclear requirements. The Product Owner, however, was able to clearly define the business objective he hopes to achieve in the Sprint.

Which of the following two actions would you support? (Choose two.)

Show Answer
Correct Answer: AD

All events in Scrum are time-boxed, meaning they have a maximum duration. Sprint Planning should not be extended beyond its designated time-box. During the Sprint, the Development Team is expected to adapt and refine the Sprint Backlog as they gain more insight into the work needed to achieve the Sprint Goal. Additionally, discussing the challenges they faced during the upcoming Sprint Retrospective allows them to identify potential improvements, making it less likely for unclear requirements to impede future planning.

Discussion

2 comments
Sign in to comment
amog
Mar 9, 2021

A and D are correct

nhungnt184Options: AD
Apr 25, 2021

Yes, A and D.