PSM II Exam QuestionsBrowse all questions from this exam

PSM II Exam - Question 8


An organization wants to apply Scrum to build a new product and has hired Steven to be the Scrum Master of three new teams that will build the first release. The organization is new to Scrum and asks Steven for advice on how to start.

Which two things should Steven first advise? (Choose two.)

Show Answer
Correct Answer: BD

In Scrum, it is essential to have a single Product Backlog to represent all of the work needed for the product to ensure there is a unified vision and prioritization of tasks. This helps in managing dependencies and achieving the overall product goal effectively. Additionally, having one Product Owner ensures accountability for maximizing value and maintaining transparency throughout the development process. A single Product Owner provides a clear point of decision making and optimizes the workflow, which is crucial for the success of Scrum implementation, especially in an organization new to Scrum.

Discussion

4 comments
Sign in to comment
nhungnt184Options: BD
Apr 24, 2021

B and D.

lenanguyen89Options: BD
May 23, 2023

B and D

Mi_WindsorOptions: BD
Jul 19, 2023

B and D are the correct answers

amogOptions: BD
Mar 9, 2021

B and D are correct