When the Developers determine that they will not be able to finish the complete forecast, who has to be present when reviewing and adjusting the Sprint work selected? (Choose the best answer.)

Show Answer
Correct Answer: C

When the Developers determine that they will not be able to finish the complete forecast, the Product Owner and the Developers need to be present when reviewing and adjusting the Sprint work selected. The Scrum framework emphasizes that only the Product Owner has the authority to make decisions regarding the prioritization and scope of work based on the business value. The Developers are responsible for estimating and committing to the work they can realistically accomplish.

Discussion

1 comment
Sign in to comment
Jyoti1010Option: C
Oct 16, 2023

Product owner and developers.