PSM II Exam - Question 173


The Sprint length should be:

Show Answer
Correct Answer: D

The Sprint length should be defined so that it is short enough to keep the business risk acceptable to the Product Owner, short enough to synchronize with other business events, and it should not exceed one month. These conditions ensure that the team can deliver value frequently, adapt to changes, and maintain alignment with business needs. Therefore, all the provided answers are correct.

Discussion

1 comment
Sign in to comment
amogOption: D
Mar 10, 2021

D are correct