A Scrum Master is working with a Scrum Team that has members in different physical locations. The Developers meet in a variety of meeting rooms and have much to do logistically (for example: reserve meeting rooms and set up conference calls) before the Daily Scrum. What action should the Scrum Master take?

Show Answer
Correct Answer: A

The Scrum framework encourages self-management and self-organization among teams. Allowing the Developers to self-manage and determine for themselves what to do aligns with the core principles of Scrum. It empowers the team to take ownership of their processes and solve logistical challenges collectively, which promotes team cohesion and autonomy.