Question 99

The Sprint Goal is a result of Sprint Planning, as is the Sprint Backlog.

    Correct Answer: A

    The Sprint Goal is indeed a result of Sprint Planning. During Sprint Planning, the Scrum Team defines what can be delivered in the Sprint and how that work will be achieved, resulting in the Sprint Backlog and the Sprint Goal. Therefore, the statement is True.

Discussion
Jyoti1010Option: A

Choice is True

Mi_WindsorOption: A

A is true